Phase I: Early Production Facility (EPF) for Three Years Period
- Conductor support structure "CSS" for 3 production wells (GNN3, GNN6 & GNN8) with a well bay supported by a MOPU
- MOPU is intended to be installed adjacent to EPF conductor support structure "CSS" and used for operating topside surface facilities and utilities.
- The GNN production to be transferred to the existing WP-C platform via two coil tube(s).
Transition phase: For Three Months Period:
- The conductor support structure for the 3 production wells is freestanding (with no support from MOPU).
- The transition phase between Phase I and Phase II is not a production phase. Production from the wells will be temporarily shut-in and the CSS shall be freestanding for a minimum period (3month) while the MOPU is demobilized and the permanent platform facility is installed. As no external units will be supporting the conductor during this phase.
Phase II: Permanent facilities:
- Will comprise a permanent platform to be installed adjacent to the three predrilled wells (CSS in Phase I). This platform will have capacity for 4/6 future wells and will include/support the existing three wells CSS. The platform shall also support all production facilities at this stage